Dependency (Project Management)In a project network, a dependency is a link amongst a project's terminal elements. There are four kinds of dependencies with respect to ordering terminal elements (in order of decreasing frequency of use): - Finish to start (FS)
- A FS B = B doesn't start before A is finished
-
- (Foundations dug) FS (Concrete poured)
- Finish to finish (FF)
- A FF B = B doesn't finish before A is finished
-
- (Entire book written) FF (Last chapter written)
- Start to finish (SF)
- A SF B = B doesn't finish before A starts
-
- (New shift started) SF (Previous shift finished)
- Start to start (SS).
- A SS B = B doesn't start before A starts
-
- (Project work started) SS (Project management activities started)
There are three kinds of dependencies with respect to the reason for the existence of dependency: - Causal (logical)
- It is impossible to edit a text before it is written
- It is illogical to pour concrete before you dig the foundations
- Resource constraints
- It is logically possible to paint four walls in a room simultaneously but there is only one painter
- Discretionary
- I want to paint the living room before painting the dining room, although I could do it the other way round, too
Traditional critical path-derived schedules are based only on causal (logical) dependencies. The critical chain method necessitates taking into account resource constraint-derived dependencies as well. See also
|
 |
|